                The marvellous Pamban bridge


                           estoration work on
                           the existing, iconic
                           Pamban rail bridge and
                           the construction of a
                           new one are taking
                Rplace simultaneously
                in the coastal  waters  of the Bay
                of Bengal,  off the  state of  Tamil
                Nadu. The iconic, 108-year-old
                Pamban cantilever rail bridge was
                commissioned in 1914 bridging
                peninsular India and the Gulf
                of Mannar,  interconnecting
                Mandapam in Rameswaram
                mainland with Rameswaram Island.
                It was the only link connecting the
                two locations until a new road                                                    Picture Courtesy: RVNL
                bridge was built parallel to the sea   metres comprising 146 spans of   movement of the lift span, besides
                link in 1988. Serving more than   steel girders, 145 spans of 12.20m   its mechanical peculiarity and a
                its codal life, the rail bridge was   length and one navigational span of   rough sea. The 550-ton lift span
                getting heavily corroded and was   61.0m length, the new bridge being   has been moved only 80 meters
                being repaired regularly by Railways   constructed will have 99 spans of   due to the curved alignment of
                in order to carry train traffic safely.  18.3m length and one navigational   the bridge, with more challenges
                                                  span of 72.5m length. It will be 3.0m   ahead in reaching the final fixing
                  Finally, rail traffic on the bridge                              point. The lift span has been
                was suspended from December       higher than the existing bridge with   designed  by  a  Spanish  firm  and
                2022 after a red alert was received   navigational air clearance of 22.0m   assembled near the coast due to
                from the sensor-based health      above sea level. Because of vertical   its massive size, contributing to the
                monitoring system installed by    lift, full horizontal width of 72.5m   complexity of the project.
                IIT Madras and Southern Railway   will be available for navigation.
                officials assessed that the bridge   This will be India’s first vertical lift   While the new rail bridge is yet
                had to be repaired due to heavy   Railway sea bridge, once the work   to get operational, it allowed
                                                  is completed.
                corrosion, to be made safe for rail                                the passage of three ships under
                operations. The Research Design    The substructure of the new bridge   its central part early this  year,
                and Standards Organisation        and navigational span are being built   attracting numerous tourists who
                (RDSO), the R&D wing of the       with the provision for double line   enjoyed the spectacular view. The
                Ministry of Railways that functions   and designed with the Railways’   suspension bridge was opened and
                as technical advisor and consultant   plan for electrification. In comparison   one ship passed travelling from Goa
                to the Railway Board and the      to existing manual operation and   to Visakhapatnam, the second from
                Zonal Railway, had been advised   control, the new bridge will have   Lakshadweep to Cuddalore in Tamil
                to inspect and suggest possible   electro-mechanical controlled systems   Nadu and the third ship from the
                repairs required to put the old   which will be interlocked with train   South to the Indian Coast Guard
                bridge back in service.           control systems.                 Station at Mandapam in the North.

                  The new Pamban bridge is         The construction of the new       The great Pamban bridge attracts
                being  executed  by Rail  Vikas   vertical-lift railway bridge has   thousands of tourists from all over
                Nigam Limited (RVNL) with whom    faced a number of engineering    the world. It transports scores
                the Southern Railway is actively   challenges due to the 2.65 degree   of pilgrims visiting the famous
                engaged. While the existing bridge   of curved alignment of the bridge   Ramanathaswamy Temple.
                structure has a total length of 2058   in its length complicating the   (Technical details courtesy: Southern Railways)