Page 58 - Trafficinfratech Magazine Aug - Sept
P. 58

INFRASTRUCTURE







                                                    Innovations                      under high hyperbaric pressures river.
                                                                                       The tunnelling alignment was such
                                                      Afcons engineers improved upon
                                                    numerous processes while planning   that it passed through several heritage
                                                                                     structures like Howrah Rail Yard,
                      The Project                   the project. Due to site constraints, the   which is one of the busiest rail yards
                                                    TBMs had to be driven through Howrah
                     incorporated the               station in advance. This was a delicate   in the country with over 670 trains
                                                                                     running daily and a footfall of over 10
                     world’s latest and             operation, where they encountered   lakh. Boring below these structures
                                                    difficulties in crossing the diaphragm
                     best practices                 walls. Afcons designed a ‘soft eye’ of   was precarious, and tunnelling was
                     in design and                  styrofoam replacing M-40 concrete,   done more than 350m below the
                                                                                     yard for each tunnel. The TBMs had
                                                    which worked extremely well for this
                     implementation                 project. This is a first design-of-its kind   to negotiate a sharp curve of radius
                     processes thereby              attempted in India by in-house design   228m, plunging into clay surface
                                                                                     and then pass by the piers of Bankim
                                                    engineers. Certain criteria in the
                     saving in time,                segmental lining were adapted and   Setu. One more curve of 226m radius
                     cost and space.                additional operational precautions and   was achieved near Rajbhavan before
                                                    checks were implemented to prevent   Esplanade station. There are very few
                                                    any untoward incidents.          examples of such tight curves being
                                                                                     undertaken in Metro tunnelling in
                                                    Execution                        the country. Despite the constraints,
                                                      A team of highly experienced tunnel   the tunnelling activity began as per
                                                    experts was deployed, should an entry   schedule, with the two TBMs covering
                                                    into the cutting chamber be required   roughly 11 to 12 metres in a day.














































            58  August-September ’19 / TrafficInfraTech                                                 www.trafficinfratech-com-500653.hostingersite.com
   53   54   55   56   57   58   59   60   61   62   63